Introduction - If you have any usage issues, please Google them yourself
This software around the me of engineering activity diagram AOE network applications, the establishment of the AOE network using a graphical interface to determine the engineering feasibility, calculation of the project activity start time, to determine the critical path and critical activities.
Specific features:
Figure AOE network known hypothetical engineering activities, try to design an algorithm requirements:
(1) to determine whether the project feasible.
(2) Find the earliest start time of each activity in the project e (i) the latest start time l (i) the projects will be completed, the earliest time
(3) to determine the key activities of the project critical path and make the whole duration of shortening
Source in a folder in the source code listing. Files in the folder "supporting documents" used in program development. Attach a separate sheet document.